How to cut maximum demand charges in Zimbabwe: seven tactics that work
Besides the units you use, you also pay for the highest power you draw in the month. That second charge is often the cheapest one to cut.
In this article
Key points
- Maximum demand is the highest average power you draw over a short interval. One short peak can set the charge for the whole month.
- The peak comes from big loads starting or running at the same time. Spreading them out costs little and lowers the peak at once.
- A low power factor pushes up demand billed in kVA, so fix the two together.
- Seven steps cover most sites, from measuring and staggering starts to power factor, batteries and a demand controller.
- Measure before you spend. Two weeks of logging shows which half-hours set the charge and which machines caused them.
A factory can use the same energy every month and still get very different bills. The difference is often the demand charge. This article explains in plain terms how that charge is formed. It then sets out seven tactics that reduce it. It is written for plant managers, financial controllers and engineers who want savings without a big capital project.
How a demand charge is formed
The utility meter averages your power over a short interval, commonly fifteen or thirty minutes. It records the highest value of the month. That highest average is your maximum demand: the highest average power you draw over a short interval. One short peak can set this charge for the whole month. It is billed at a rate per unit of demand, however briefly it lasted. So two plants that use the same energy each month can pay different amounts. One has a flat load. The other has sharp peaks.
The reason is physical. The network, the transformer and the cables must be sized for the highest power you can ask for, even if you ask for it rarely. The demand charge pays for keeping that capacity ready for you.
Demand, explained
Demand is not the power at one instant. It is the average power over a fixed interval chosen by the utility. The charge is set by the highest interval in the month. So a spike that lasts less than the interval is partly averaged away. A longer interval is kinder to a plant with brief peaks. Our guide to power factor explains how power is measured in kW and kVA.
A worked example
Say a plant averages 400 kVA. Twice a week, three large compressors and a chiller start together, and the meter records 520 kVA. For this example, use the 11 kV capacity charge in the December 2023 ZETDC schedule, US$10.18 per kVA. The billed demand is 520 kVA, so the charge is US$5,294. Now suppose the starts are put in order and the peak falls to 440 kVA. The charge becomes US$4,479. You save US$815 a month, or about US$9,780 a year. Production does not change, and neither does energy use.
Peak shaving, with numbers
The yearly saving is easy to work out: your demand rate × the kVA you cut × 12 months. Sometimes a battery delivers the cut. For a rule of thumb, size the battery at your peak kVA times the hours the peak lasts, plus about 15% for losses and to avoid draining it flat.
| Item | Example |
|---|---|
| Demand rate (11 kV, December 2023 ZETDC schedule) | US$10.18 per kVA a month |
| Peak to cut | 50 kVA, lasting 30 minutes |
| Battery size needed | about 29 kWh (50 kVA × 0.5 h, plus 15%) |
| Installed cost at US$320 per kWh | about US$9,357 |
| Saving per year | 12 × 10.18 × 50 = US$6,108 |
| Simple payback | about 1.5 years |
The same sums for a staggered-start rule, which costs nothing, show why the cheap tactics come first.
Seven tactics, in order of cost
- Measure the load profile. Fit a logger at the main incomer for at least two weeks. Then read the half-hours that set the peak. The profile tells you which tactic is worth paying for. It usually shows that two or three events create most of the charge.
- Sequence large starts. Start compressors, mills, chillers and kilns a few minutes apart. This is an operating instruction, not an investment. It often removes the highest peak at once.
- Use soft starters or drives on large motors. A motor started directly from the supply draws several times its rated current for a short time. A soft starter or a variable-speed drive limits that surge. A variable-speed drive is a controller that changes a motor's speed to match the work, so it uses less power when the load is light. Limiting the surge lowers the short peak that the meter averages.
- Shift flexible loads. Batch processes, water pumping, battery charging and cold-room pre-cooling can often move to a quieter period. Moving a load does not change the energy it uses. It only changes when it uses it.
- Correct the power factor. Power factor shows how much of the power you draw is actually useful. A figure of 1.00 is perfect. Motors, transformers and welders pull it down, and a low figure costs you extra. Where demand is billed in kVA, a low power factor inflates it. A capacitor bank is a set of capacitors that supply reactive power on site. A bank that is sized correctly lowers kVA for the same useful load. Where there are harmonics, the bank must be detuned. Harmonics are distortion of the electrical waveform, caused by drives, LED lights and inverters. Our power factor guide explains the method.
- Shave the peak with storage or a generator. A battery or a standby generator can supply part of the load during the few half-hours that set the peak. The grid then sees a lower maximum. This needs a controller and a clear money case, so it comes after the cheaper tactics.
- Automate with a demand controller. A controller watches the running demand. It delays or switches off agreed loads before the interval closes. It turns the earlier tactics into a standing rule that does not depend on an operator paying attention.
What to protect while you reduce demand
Do not switch off cold rooms, process ovens or any load with a quality or safety limit without a set limit on how long it may be off. Water, cooling and compressed air hold their effect for a while after you stop them. That is why they are good candidates for short delays.
Calculated at the December 2023 ZETDC rate; check your current bill. Source: ZETDC tariff schedule of 1 December 2023; AVEX GRID calculation.
Where the saving shows on the bill
| Tactic | Typical cost | Effect on the bill |
|---|---|---|
| Load profile | Low | Shows which events set the peak |
| Sequenced starts | No capital | Lower billed demand |
| Soft starters and drives | Moderate | Lower start-up peaks and often lower energy use |
| Load shifting | Low to moderate | Lower billed demand |
| Power factor correction | Moderate | Lower kVA demand and lower reactive charges |
| Storage or generator peak shaving | Higher | Lower billed demand during peak half-hours |
| Demand controller | Moderate | Keeps the saving in place automatically |
How AVEX GRID helps
- Bill and profile review. We read 12 to 24 months of bills. We log the main incomer and find the events that set your demand.
- A ranked saving plan. We cost each tactic and show the yearly saving and the payback, so your finance team can decide.
- Design and commissioning. Where you need equipment, we specify it and check it in ETAP. Then we verify the result on your next bills.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
What is the fastest way to lower a demand charge?
Sequence the starting of large loads and find the peak events with a load profile. This usually needs no capital and can lower the next bill.
Does lowering demand reduce my kWh use?
Not by itself. Demand management changes when you use power, not how much. Savings on kWh come from efficiency measures such as drives, right-sized motors and leak repair.
Is a battery worth it for demand charges?
It can be, where a few half-hours set the peak and the demand rate is high enough. We test the case with your load profile before recommending it.
How long should I log my load?
At least two weeks that include your busiest shifts. A full month gives a clearer picture, because the billed demand is set by the highest interval of the month.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.
- IEEE Std 1459-2010: definitions for the measurement of electric power quantities
- ZETDC: Electricity tariffs as at 1 December 2023 (archived copy)
- Commercial Farmers' Union: ZESA tariff notice (maximum demand and reactive energy terms)
- ISO 50001: energy management systems
- IEC 61000-4-30: power-quality measurement methods
- ZERA: Zimbabwe Energy Regulatory Authority