Powering a mine in Zimbabwe: grid, diesel or solar plus storage?
A mine cannot stop when the grid goes down. Where will reliable, affordable power come from, and who carries the risk?
In this article
Key points
- The grid is short: about 1,537 MW in 2025 against peak demand near 2,200 MW, with town cuts of up to 20 hours a day.
- Mines have four options: grid only, grid plus diesel, solar with batteries, or a supply contract. Most end up with a mix.
- Own-use solar for mines is regulated by ZERA. Check the current rules for your plant size before you design.
- Chinese-backed projects are leading. Prospect Lithium, linked to Huayou, is building a 70 MW off-grid solar plant for lithium processing.
- Decide using your load profile, a grid impact study and a hybrid model, not a brochure. That is what a feasibility study does.
在津巴布韦为矿山供电:电网、柴油,还是光伏加储能?
- 津巴布韦电力供应紧张。据报道,2025年平均发电约1,537兆瓦,而高峰需求估计约2,200兆瓦;2025年10月城市限电最长达每天约20小时。
- 矿山有四种供电方式:纯电网、电网加柴油备用、自建光伏加储能、第三方供电合同。大多数矿山最终采用混合方案。
- 自用光伏发电需要向津巴布韦能源监管局(ZERA)申请许可。据报道,到2024年ZERA已为工业用户的现场发电项目发放了约200兆瓦的许可。
- 据报道,华友钴业旗下的Prospect Lithium正在为津巴布韦的锂加工建设70兆瓦离网光伏电站。
- 据报道,2026年第122号法令(能源管理条例)适用于装机容量不低于100 kVA或按最大需量计费的用户,矿山需要定期能源审计。请以政府公报原文为准。
- AVEX GRID 提供可行性研究、ETAP 电网影响分析、ZERA 许可技术文件和业主工程师服务,可为海外团队远程协作(英文沟通)。
联系方式:WhatsApp +7 900 131 7406,邮箱 inquiries@avexgrid.com。
Zimbabwe's mining story is no longer only about gold and platinum. Lithium, chrome and nickel projects have drawn large foreign capital, including from China. Every one of them depends on electricity. This article sets out the power choices a mine has, how to compare them, and what the approval path looks like. It is written for mine managers, owners, and the investors and lenders behind them.
The supply gap, in numbers
Reports from late 2025 describe a grid that generates well below peak demand. Hwange thermal power station and Kariba hydropower supply most of the power. Kariba is sensitive to drought. In 2025 its output fell from an installed 1,050 MW to a few hundred megawatts, before water allocations improved. A megawatt (MW) is 1,000 kilowatts, or 1 million watts. Independent producers added only a small share.
The World Bank has estimated that power shortages cost Zimbabwe about 6.1% of GDP a year. For a mine, the cost shows up as lost hours, damaged equipment and diesel bills. Load-shedding means planned power cuts when there is not enough electricity for everyone. The government has set targets to end it, and they have repeatedly slipped. The latest target is the end of 2027. A mine plan that assumes a reliable grid carries hidden risk.
Figures as reported; peak demand is an estimate. Source: ZERA and press reports
Four ways to power a mine
| Option | Strengths | Weaknesses | Best for |
|---|---|---|---|
| Grid only | Lowest capex; simple | Outages and low voltage; exposed to tariff changes; new connections can take time | Small, flexible operations |
| Grid plus diesel back-up | Familiar; fast to install | Fuel cost and logistics; maintenance; emissions that investors increasingly question | Short-term bridging |
| On-site solar plus storage (own-consumption) | Cheap daytime energy; cuts diesel and demand charges; hedges tariff risk | Capex; must be engineered around the load; storage adds cost | Most medium and large mines |
| Third-party supply (IPP or wheeling) | No capex for the mine; long contract | Contract and counter-party risk; licensing and wheeling terms | Large loads, investors who prefer opex |
In practice most mines build a hybrid. The grid stays connected for stability. Solar covers the day. Batteries shave the peaks and carry you through short outages. Diesel becomes the last resort instead of the default.
Does solar work on a 24-hour load? A worked example
Mining and mineral processing often run around the clock, but solar makes power only in daylight. A simple calculation shows why design matters. These assumptions are worked figures, not measurements:
- The average load is 5 MW, running 24 hours a day. That is 5 MW × 8,760 hours = 43,800 MWh a year.
- The solar plant is 6 MWp. Most of Zimbabwe yields roughly 1,600 to 1,800 kWh per kWp per year. A kilowatt-hour (kWh) is the energy of 1,000 watts used for one hour, and it is the unit your meter counts and your bill charges for. A kWp, or kilowatt-peak, is the rated size of a solar array in standard test conditions. The Global Solar Atlas gives a figure for any site. At 1,700 kWh/kWp, this plant makes about 10,200 MWh a year.
- Solar then supplies about 23% of the annual energy, before losses and curtailment, and without storage.
That 23% is real money. It is daytime energy that would otherwise come from the grid or from diesel. Batteries let some of the daytime surplus serve the evening. But each extra hour of storage adds cost, so the right size is a calculation, not a guess. The answer depends on your diesel price, your grid tariff and outage record, the shape of your load and the cost of capital.
What the licensing path looks like
- Registration or licence. Under SI 126 of 2026, a plant for your own use from 100 kW to 10 MW must register with ZERA before building. Above 10 MW you need a licence from the Zimbabwe Energy Regulatory Authority (ZERA), which licenses energy businesses and approves tariffs. ZERA's board considers applications on a quarterly cycle. AVEX GRID confirms the current position for your project as part of the scope.
- Regulations. The relevant framework includes the Electricity Act, the licensing regulations and the net-metering regulations. News reports also describe own-consumption licensing regulations approved in 2026.
- Grid connection. If the plant connects to the network, ZETDC will want a grid-impact study. ZETDC is the Zimbabwe Electricity Transmission and Distribution Company, which sells you power and sends the bill. The study shows three things. Load flow is a calculation of how power moves through a network and what the voltages are along the way. Short-circuit levels show how big a fault current could get. Protection coordination means setting breakers and relays so the one nearest a fault trips first and the rest of the plant keeps running. This is power-system engineering. Engineers typically do it in software such as ETAP.
- Wheeling. Wheeling means using the grid to carry power from a generator to a customer. In 2024, a wheeling fee of about US 1.25 cents per kWh was agreed with the Intensive Energy User Group for users connected to the transmission network. We confirm the current figure for your site.
- Energy-management rules. SI 122 of 2026 applies to facilities of at least 100 kVA, or maximum-demand customers. kVA is the size of the load on your supply. So most mines will need an energy policy, a licensed energy manager and regular audits.
Lessons from the lithium belt
Prospect Lithium, linked to Huayou, is building a US$400 million lithium sulphate processing plant. A 70 MW off-grid solar plant is under construction to power the early stages of processing. The reason is simple. Power scarcity pushed the project away from a planned coal-fired plant and towards solar. Whatever the final set-up, the pattern is clear. When capital is large and power is uncertain, on-site generation stops being "nice to have". It becomes a condition for getting finance.
How to decide: the five-step feasibility route
- Measure the load. Collect interval data on the main incomer and the largest consumers, over a representative period.
- Model the options. Compare grid, diesel, solar and storage combinations over 15 to 25 years. Use your real fuel price, tariff and outage data.
- Study the grid impact. Run load flow, short circuit and protection studies for the preferred option, so the connection is approved the first time. A short circuit is a fault where current takes an unintended path with very little resistance, so a very large current flows.
- Prepare the technical file. These are the documents ZERA, ZETDC and lenders will read.
- Protect the build. An owner's engineer reviews contractor designs, witnesses testing and manages commissioning, so the plant performs as modelled.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
Can a mine in Zimbabwe generate its own power?
Yes. Under SI 126 of 2026, own-use plants from 100 kW to 10 MW register with ZERA before building, and plants above 10 MW need a licence. The process, fees and thresholds should be confirmed with ZERA, because rules and fee exemptions have been changing.
Is solar enough for a mine that runs 24 hours a day?
Solar alone covers the daytime share of the load. Batteries and the grid, or in some cases a small diesel set, cover the rest. The mix is chosen with a hybrid model.
How long does it take to get approval?
wide variation, from months to more than two years for larger projects. Early engagement with ZERA and ZETDC, and a complete technical file, shortens it.
Can overseas investors use AVEX GRID remotely?
Yes. We model remotely, then support site data collection, regulator meetings and commissioning in Zimbabwe.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.
- Herald: Power production surges as government targets US$9 billion energy investment
- AllAfrica: Zimbabwe faces intensified power cuts as ZESA shuts down Hwange Unit 8 (Oct 2025)
- China Global South Project: Huayou unit to build 70 MW solar plant for lithium processing (5 Nov 2025)
- CrossBoundary Energy: Distributed energy resources regulation, Zimbabwe (Aug 2024)
- Afriwise: Electricity (Energy Management) Regulations, S.I. 122/26
- Global Solar Atlas (solar yield for any site)
- The Herald: ZERA licenses 440 MW generation projects in Matabeleland North and Midlands