Net metering in Zimbabwe, step by step: from design to the commissioning test

Net metering lets you send extra solar power to the grid. The technology is simple; the paperwork is a chain, and one missing document delays everything.

In this article
  1. What net metering means
  2. The five stages
  3. Stage 1: Design for the connection rules
  4. Stage 2: The technical file
  5. Stage 3: Approval and agreement
  6. Stage 4: Installation and metering
  7. Stage 5: The commissioning test
  8. Avoiding delays
  9. What the rules set, and what is still unclear
  10. Fees, forms and timelines to ask about
  11. The technical requirements behind the paperwork
  12. What to keep on file
  13. Why applications are sent back
  14. A realistic programme
  15. How AVEX GRID helps

Key points

  • Net metering is covered by SI 86 of 2018. You stay a ZETDC customer and the power you export is set off against what you use.
  • There are five stages: design, application to ZETDC, approval and connection agreement, installation with a two-way meter, and a commissioning test.
  • A complete file, with a single-line diagram and equipment datasheets, shortens the review.
  • Your inverter must meet ZETDC rules, including anti-islanding protection that switches the system off when the grid is down.
  • Plan the design, paperwork and installation as one job. Buying equipment before approval is the most common cause of delay.

This article follows one grid-tied solar system from the first design to the day it is registered and metered. It adds to our wider guide to own-consumption solar and net metering. Here you get a practical sequence you can plan around.

What net metering means

A net-metered customer makes electricity on site, uses what is needed and sends any extra to the grid. A two-way meter records both flows. The utility sets the exported energy off against the imported energy in the billing period. You pay for the difference. Depending on the arrangement, you may carry a credit forward. The exact terms are in the regulations and the utility rules for your tariff class.

The five stages

StageWhat happensWhat you prepare
1. DesignThe system is sized to your load and the connection rulesLoad data, site layout and choice of equipment
2. ApplicationThe utility receives your application and reviews itApplication forms, single-line diagram and datasheets
3. ApprovalThe utility approves and sets the connection termsSigned connection agreement and any required fees
4. InstallationThe system is built and the two-way meter is fittedA qualified installer, protection settings and labelling
5. CommissioningThe utility watches a test and registers the systemTest records and drawings of what was built

Stage 1: Design for the connection rules

The design must respect the capacity of your supply and the utility's technical requirements. The key items are the inverter ratings, the protection settings, the cable sizes and the point of connection. The design also decides how much of the energy you will use on site. That sets the value of the plant.

Stage 2: The technical file

  • A single-line diagram showing the array, the inverters, the protection and the point of connection.
  • Datasheets and certificates for the inverters and the panels.
  • The protection settings, including how the system behaves with anti-islanding.
  • A site layout and the contact details of your installer.
Do not buy equipment firstThe utility may require certain inverter features or settings. Confirm the approval route before you order. Then the equipment you buy is the equipment that will be approved.

Stage 3: Approval and agreement

After the review, the utility may ask for changes, or approve with conditions. A connection agreement sets the terms for exporting power and the duties of each side. Keep every version of the file. Questions about it often come up years later.

Stage 4: Installation and metering

A qualified installer builds the system to the approved design. The utility fits or approves a two-way meter. Before the test, check the earthing, the labelling, the isolation points and the protection settings. The test will look for them.

Stage 5: The commissioning test

The utility watches a test. It normally checks the protection and confirms that the system disconnects when the grid is lost. It also checks that the meter records both import and export. After a successful test, you are registered as a participant.

Own-consumption solar registered with ZERA against the 100 MW targetMegawatts, end of 2025
  • Registered, as a share of the 100 MW target73.7 MW

Source: ZERA

Avoiding delays

  1. Prepare the whole file before you submit it. Missing items restart the review.
  2. Match the design to the utility's requirements from the start.
  3. Appoint one person to handle the letters and emails and keep copies.
  4. Plan the installation after approval, not before.

What the rules set, and what is still unclear

The rules are the Electricity (Net Metering) Regulations, Statutory Instrument (SI) 86 of 2018. They first capped a net-metered system at 100 kW. A change was gazetted in 2022. ZERA identifies it as SI 38 of 2022. It raised the cap to 5 MW. So a factory or a mine can now use the route first designed for homes and small businesses. The press reports that exported power earns a credit against your electricity bill, not cash. Reports from 2021 describe a credit of 0.9 kWh for each kWh exported. Later reports in 2023 describe ZETDC starting to buy extra power from households and businesses. We cannot settle this from the sources we have. So ask ZETDC for the current terms in writing. Then design the plant so the answer matters little, by sizing it for your own use.

The sums show why. A 100 kWp system that exports 20 MWh in a year, credited at 0.9, offsets 18 MWh of later imports. The 2 MWh difference is the cost of using the grid as a store. It is small compared with what you lose if an oversized plant exports most of its output. Net metering is a safety valve for extra power. It is not the business case.

Fees, forms and timelines to ask about

The utility sets connection and administration fees, subject to ZERA approval, and they change. One report put the total for a small single-phase customer at about US$632, including the two-way meter. Treat that as a guide and ask for the current fee schedule. At the start, ask the same office five questions. Which application form applies to your tariff class? Which technical documents does it need? Must the inverter be on an approved list? How long is the review expected to take? Who watches the commissioning test? Put the answers in your project programme. A review queue can add weeks that a contractor will not absorb.

The technical requirements behind the paperwork

The utility's checks come down to one question: will your plant behave on its network? An inverter must stop exporting when the grid goes off. This is called anti-islanding. It protects line workers from power coming back from your roof. The inverter must also stay within voltage and frequency limits. Where the rules require it, it must ride through short disturbances. It must also keep distortion of the power waveform and flicker within accepted limits. International standards show the expected behaviour, even where the local rule is shorter. These are IEEE 1547 for connecting generators to the grid and IEEE 519 for harmonics. The protection settings on your inverter datasheet should match the settings the utility requires. State them in the application. A mismatch is a common reason for a request for changes.

Above the net-metering cap, or for a plant that sells to other parties, the route changes to a generation licence from ZERA. It has its own application form, business plan and company documents. The form was revised in July 2026 and carries an application fee. Check the current version on the ZERA website. The two routes are separate, and choosing the wrong one costs months.

What to keep on file

Registration is not the end. Keep a folder with the approved design, the signed connection agreement and the commissioning record. Add the settings of every protection device and the drawings of what was built. Say the inverter is replaced in year eight, or the roof is reworked, or a lender asks for proof of compliance. That folder turns a week of searching into an afternoon. On the day of commissioning, record the meter serial number and the first import and export readings. Then you can check the first bill against a known starting point.

Why applications are sent back

Reviews tend to stall on the same few points. You can fix all of them before you send the file. The single-line diagram does not show the protection or the point of connection. The inverter datasheet is missing, or the model on the drawing differs from the model on the quotation. The capacity you declare is more than your supply can carry, so the utility asks for a supply upgrade that nobody budgeted. The application names a site owner who is not the account holder. This happens when a tenant installs a system on a landlord's building. Finally, the installer is not qualified to sign the electrical certificate. Use a short checklist, signed off by someone other than the person who wrote the file. It catches most of these.

A realistic programme

Treat the process as a sequence with waiting periods built in. Design and the technical file take a few weeks if the load data exists. You do not control the utility review. So plan to buy equipment after approval, not before. Installing a commercial rooftop plant usually takes weeks, not months. Commissioning is a single visit that the utility witnesses. The utility's engineer, the installer and the owner's representative must be in the same place on the same day. Book it as soon as the installation date is firm, and have the test records ready on paper. If the date slips, tell the utility early. A rescheduled test costs more time than a late one that was announced.

How AVEX GRID helps

  • Design and technical file prepared for ZERA and ZETDC to review.
  • Programme management from application to commissioning.
  • Test support, so that you pass the commissioning checks at the first attempt.

What AVEX GRID can take off your hands

AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.

Feasibility and bankable studiesYield, load and hybrid models, and the technical file lenders and ZERA read.
Power-system engineering (ETAP)Load flow, short circuit, arc flash and protection studies for approvals and safe design.
Licence and PPA technical supportZERA licence documents, ZETDC connection studies, PPA technical schedules.
Owner's engineerDesign review, testing and commissioning on your side of the EPC table.
Tariff, audit and compliance workMaximum-demand and power-factor savings, readiness for energy-management rules.
Remote plus on the groundModelling for overseas teams, with an engineer in Zimbabwe for site, utility and regulator work.

We quote fixed prices after a free scoping call and reply the same working day.

Frequently asked questions

What is the size limit for net metering?

SI 86 of 2018 first capped systems at 100 kW. A change gazetted in 2022, which ZERA identifies as SI 38 of 2022, raised the cap to 5 MW. Larger plants, or plants that supply other parties, need a generation licence.

What do I get for the energy I export?

Press reports describe a credit against your bill. One report gives 0.9 kWh of credit per kWh exported. Later reports say ZETDC buys extra power. The terms may change. Confirm them with ZETDC in writing and size the plant mainly for your own use.

Who approves a net-metered system?

The utility that supplies you reviews and approves the connection, within the rules set by the regulator. We prepare the file for both.

Can I export all of my solar output?

Net metering is designed for customers who use most of the energy on site and export the extra. Your agreement states the terms.

Do I need a special meter?

Yes, a two-way meter that records import and export. The utility normally fits or approves it.

How long does the process take?

It depends on how complete your file is and how long the utility queue is. A complete file and an approved design remove most delays.

Topics: net metering ZimbabweZETDC net metering applicationZERA net meteringgrid-tied solar registrationSI 86 of 2018solar export Zimbabwesmart meter net meteringenergy consultant Zimbabwe

Sources and notes

General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.

DJ

Devine Tafara Javangwe is the founder and lead consulting engineer at AVEX GRID. He holds an MSc in Electrical Power Engineering (Southern Federal University, 2025), is a Professional Member of the Zimbabwe Institution of Engineers and an IEEE member.

About the practice · Contact

Get your solar registered without false starts.

Share your design or your bills. We prepare the technical file and manage the path to a successful commissioning test.

+263 78 488 9775 · Autherstone Street 21, Marondera, Zimbabwe · Remote across Southern Africa