Energy audit preparation checklist: what to have ready before the auditor arrives
Auditors lose their first days hunting for information you already have. Get it ready beforehand, and their time goes into finding savings.
In this article
Key points
- Good preparation has four parts: electricity data, process and equipment data, people, and access to the site.
- Twelve to twenty-four months of bills and the same period of production figures are the most valuable inputs.
- A list of the ten largest loads, with nameplate data and operating hours, usually accounts for most of the energy used.
- Name one accountable person and one deputy. Audits stall when nobody can open a door, a drawing or a data file.
- A readiness review before a formal audit organises the records and often finds early savings that fund the audit itself.
An energy audit is a measured investigation. It shows where a site uses energy and which changes would cut the cost. The result is only as good as the information you give the auditor. This checklist follows the order in which most auditors ask for information.
Electricity and fuel records
- Electricity bills for the last 12 to 24 months. Include the tariff class (the price list for your electricity) and your declared supply capacity.
- Fuel purchase records for generators, boilers and vehicles, with delivery dates and quantities.
- Any sub-meter readings, and the date each meter was last checked. A sub-meter is a meter on one part of a site, such as a machine or a tenant, so its use can be measured separately.
- The single-line diagram, even if it is hand drawn. This is a simple drawing that shows how the parts of your electrical system connect. Add a note of your transformer ratings. A transformer raises or lowers the voltage so electricity can travel on the grid and be used safely on site.
Production and operating data
- Monthly output in the units that matter to your business, such as tonnes, litres or units produced.
- Shift patterns, planned stoppages and the months when output is seasonal.
- Major changes during the period: new machines, expansions, closures or process changes.
Production data lets the auditor tell a real saving from a slow month. Without it, every difference in consumption is open to argument.
Equipment list
| Group | Information to collect |
|---|---|
| Motors, pumps and fans | Rated power, age, control method, annual operating hours |
| Compressed air | Compressor ratings, pressure setpoint, known leaks, operating hours |
| Cooling and refrigeration | Plant ratings, setpoints, defrost method, condenser condition |
| Heating and process | Boiler or furnace ratings, fuel, temperature setpoints |
| Lighting and buildings | Fitting types, counts, hours, building controls |
| Self-generation | Solar, generator and battery ratings and logged output where available |
People and access
- A maintenance contact who knows the plant history and the faults that keep coming back.
- A finance contact who can confirm costs and the rules for approving investment.
- Safe access to switch rooms, plant rooms and roofs, with the permits your site requires.
Measurements the auditor will take
Expect the auditor to fit loggers on the main incomer and on the largest loads. They stay for at least one full operating cycle. The auditor will also take spot readings with portable instruments. Loggers record power, voltage, current and power factor over time. Power factor shows how much of the power you draw is actually useful. A figure of 1.00 is perfect. Motors, transformers and welders pull it down, and a low figure costs you extra. Loggers turn nameplate guesses into measured profiles. That is why you can defend the findings in front of a finance committee or a regulator.
A 90-day preparation plan
- Days 1 to 30. Collect bills, production data and fuel records. Appoint the contacts. Start a single folder for all documents.
- Days 31 to 60. Build the equipment list, mark the ten largest loads and confirm how your meters are arranged. Fix any obvious leaks or faults that could distort the measurements.
- Days 61 to 90. Run a readiness review. Check the data for gaps, agree the audit scope and schedule the measurements around production.
What a good data pack looks like
A well-prepared pack saves days on site. It also makes the findings easier to trust.
- Bills. Twelve to twenty-four months of electricity bills for every meter, together with the fuel records for any generators or boilers. Mark any gaps and estimated readings.
- A single-line diagram. Even a hand-drawn sketch that shows the incomers, the main boards and the large loads is better than nothing.
- A list of the main loads. Motors, chillers, compressors, pumps and furnaces, with their ratings and how many hours they run. Say whether they run all year or by season.
- Production or occupancy figures for the same months as the bills, so the energy can be compared with output.
- Metering information. Which loads have their own meters, which are sub-metered, and where the data is kept.
- Earlier reports and changes. Previous audits, major equipment changes, and maintenance records for the large plant.
The gaps that cost the most time
The same few gaps hold up most audits. Bills may cover only part of the year. There may be no list of the large loads. Energy use may not be tied to production. These gaps are easy to close before the visit and expensive to close after it. If a figure is missing, say so. An honest gap, noted in the pack, is far more useful than a number that was guessed.
How AVEX GRID helps
- Readiness review. We organise your records, find the likely savings and prepare the structure of the investment plan before the formal audit.
- Measurement support. We specify and install loggers and read the results with you.
- Clear outputs. You receive ranked measures with cost, saving and payback. They come in a format your board can use.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
How long does audit preparation take?
Most sites need four to eight weeks to collect bills, production data and equipment lists. A readiness review can run in parallel.
Do I need sub-meters before an audit?
They help, but they are not required. Temporary loggers can measure the main loads during the audit.
What if my records are incomplete?
Start with what you have. We identify the gaps, estimate what can be recovered and plan measurements to fill the rest.
Who should attend the first meeting?
The accountable contact, a maintenance lead and a finance representative. That group can answer technical questions and agree what is worth doing.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.